Overtime report

Hello Everyone.
Is it possible to generate some kind of report, on with we can find how much overtime (or "under-time") every user done on every day in month.

E.c. Kowalski has worked 6 hours on 6th february (and it is 2 hours below the standart working time for a day) -> "-2:00" in report.
Then, Kowalski spend 10 hours at work on 8th february , and in the report we will see "+2 hours".

Hello Dawid, 

It depends if you would like to create report from spent time or from attendance. 

1. Spent time report = Go to Project list>spent time http://prntscr.com/r53aiy>set filter user and correct date and columns for spent time and Estimated time = In this report you can compare how much time this user was suppose to work with actual spent time

2. Attendance report = Go to attendance>choose list>click on pencil to change the filter http://prntscr.com/r53b35>as before filter user and correct date and columns such a attendance duration and working time to compare it.

Hope this is what you were looking for

Thank you

Martina