Hello,

if I choose "Enable copying of task comments to parent task" in the project setting, then the check box "Copy comments to parent" is ticked by default.

Is there any additional setting, where I can affect the default behavior of this check box?

Thank you,
Martin Zlamal

Posted in How to reschedule all the tasks in a project?

Thank you! I'm quite sure, I had tried the second possibility (in the global Gantt) and it didn’t work. But we are still testing and slightly changing system environment settings. Could be that behavior affected by a parameter?

Hello, my question concerns rather the project administration than the ER settings. Can you please advise me on how to quickly reschedule all the tasks or a selection of tasks under a project or a milestone at least? If I change the project end date, nothing actually happens. And moving tasks subsequently in the Gantt chart is not that efficient, besides it's practically usable only by setting the timescale to days which costs more scrolling.